The Broad St. project is moving along!
Currently the contractor is working in the intersection of S. Logan and E. Broad St. Businesses are open between Abbe Rd. S. and S. Logan. However, the Huntington Bank complex (860 E. Broad is accessed via S. Logan only). Depending on weather, the contractor will be excavating between Longson to Abbe Rd. S, on Wednesday or Thursday. They will be excavating the east bound lane (towards SR 57).
West bound traffic will be able to access Dunkin thru Longson Ave. Signage has been posted for this as well.
As always, we appreciate patience, reducing speeds, and safe driving!